1959 : REEL’s “Jumbo” dig the Mont-Blanc tunnel

50 years ago  : 1959 – The « Jumbo » of REEL dig the Mont-Blanc tunnel.

Ordered by BORIE SA, designed and manufactured by REEL, the Jumbo is a 75 tons machine, 9 meters high, 8 meters wide and 20 et 20 of length.

It carries 16 air drills and 25 employees.

The 140 holes made at each station are then loaded with explosives and the rock is emptied by wagons …

The average advance of 8 meters  per day, thanks to the Jumbo, allows the French to finish before the Italians on the 14th of August 1962 …

The breakthrough of the Mont-Blanc: A wild race between the French and the Italians !

 

Join a dynamic group! we are always on the lookout for new talents!
Reel hire all over the world

REEL receives the first DNV ISO 19443 certificate

REEL becomes the first company in the world certified by DNV according to ISO 19443!

REEL at the 2022 SOLIDS Dortmund exhibition – Come and meet us!

Our teams are waiting for you 22 to 23 of June at the Dortmund exhibition center!

ITER : TOKAMAK ASSEMBLY | The big lift featuring REEL!

The first section of the plasma chamber was lifted and transferred from the assembly tool to the pit by REEL cranes.

ITER : TOKAMAK ASSEMBLY | The big lift featuring REEL!

The first section of the plasma chamber was lifted and transferred from the assembly tool to the pit by REEL cranes.